Grid & development
Your Data Center Is Ready. The Utility Says 2032.
A completed building can wait years for its full utility connection. The carrying costs and lost operating time are changing how developers compare sites and power options.

A finished data center can be an expensive place to wait. The building is complete, cooling is installed and customers want capacity, but the utility work needed to serve the campus is still years away. Meanwhile, capital remains tied up in a facility that cannot operate at its intended load.
How much power is available on opening day?
Power for initial testing may arrive well before power for a fully occupied campus. That can allow commissioning to begin while a transmission extension or substation is still under construction. For the developer, the difference shows up in how many data halls can actually open and earn revenue.
Dominion Energy's published connection guidance describes staged service aligned with a facility's expected load ramp. It says projects below 50 megawatts can frequently use existing distribution infrastructure and typically take one to two years from initial planning discussions. Projects above 50 megawatts will most likely require transmission extensions and a new substation.
Each stage of service needs a capacity commitment and a date. With those in hand, the developer can align financing, server deliveries and tenant commitments with the load the utility expects to serve. Later phases may depend on a very different construction schedule from the first building.
What sits behind a connection date
The Edsall substation and transmission project in Fairfax County supports new data center development as well as area reliability. Dominion's legal record gives July 26, 2024 as its application date and August 8, 2025 as the state commission's approval date. Its published schedule targets energization in the second quarter of 2028, with substation construction scheduled from the second quarter of 2027.
In Prince William County, the Hornbaker–Devlin project involves double-circuit 230-kilovolt transmission and a switching station supporting data center growth. Dominion filed its application on March 14, 2025 and received approval on December 11, 2025. Its anticipated schedule targets spring 2028 energization; initial project evaluation dates back to summer 2023.
In both cases, approval is followed by years of procurement, construction and testing. The published energization date reflects that work across the network, including facilities outside the developer's property and control.
Dublin's proposed gas-powered bridge
In Dublin, the wait for utility service prompted Equinix to propose onsite gas generation for its DB8 development at Profile Park. The December 2024 planning inspector's report describes the applicant's expected six-to-eight-year wait for electricity and the proposed use of gas generation during that period.
The appeal was refused on February 19, 2025. The gas-generation proposal required its own planning approval, leaving the interim supply strategy dependent on another consent.
The work may extend far beyond the property
A transmission line running beside a prospective site can be reassuring during a land search. Its available capacity still depends on the wider network and the ability to maintain service during outages. Serving another campus may require work at substations or on circuits some distance away.
That makes the utility schedule harder to control than the building schedule. Rights of way, road crossings, work at neighboring substations and planned construction outages can all affect progress. Some work can overlap; other tasks have to wait for an approval, delivery or earlier stage to finish.
Equipment manufacturing can extend the wait further. The Department of Energy's July 2024 large power transformer report documented producer discussions describing lead times reaching or exceeding 36 months. An individual project then needs a confirmed manufacturing slot, transport arrangements and time to install the equipment after it arrives.
The cost of an idle investment
For a hypothetical project with $100 million invested and an annual carrying cost of 8 percent, a one-year energization delay adds $8 million in simple carrying cost. That is before offsets, mitigation or compounding, and before accounting for the business the facility was expected to support.
Lost operating income can add to that exposure. Its size depends on the contribution the facility would have earned after operating expenses, when leases commence and what remedies customers have for delayed service. Some demand may move to another location; some may be lost. Those contract details can change the cost of the same construction delay considerably.
Server procurement adds another decision. Ordering early can secure a delivery slot, but equipment may spend months in storage while newer technology reaches the market. Waiting preserves capital and reduces that exposure, with the risk that delivery slots will no longer line up with the revised opening date.
Onsite generation brings its own schedule
Generating onsite can support a campus during the wait or become its permanent supply. In either case, the work extends well beyond ordering engines. Fuel supply, emissions approval, noise control, electrical distribution and plant controls all have to be ready, along with maintenance access and the people who will operate the installation.
For a bridge measured in years, generator duty and operating permissions become major design decisions. EPA's May 1, 2025 clarification addressed certain engines operating up to 50 hours annually under qualifying non-emergency grid-support arrangements. That provision concerns limited grid-support operation; a fleet intended to supply a campus continuously needs a rating and authorization covering that use.
Gas supply can introduce another construction project. A pipeline extension or pressure-management equipment may be needed before the generating plant can carry its intended load. For a temporary installation, the eventual switch to permanent service also needs to be designed and scheduled, including any interruption required for the changeover.
A generating station next door can still leave a wait
At Susquehanna, the delivery arrangements became the subject of a federal decision. On November 1, 2024, FERC rejected an amended interconnection agreement that would have raised co-located load from 300 to 480 megawatts. FERC's decision was specific to the proposed interconnection agreement.
The parties later changed the arrangement. In June 2025, Talen announced an expanded agreement with Amazon and a planned transition to front-of-the-meter service after transmission reconfiguration, then expected in spring 2026. The announcement described power entering PJM and PPL providing transmission and delivery.
The Susquehanna history shows how the route to service can change through agreements, regulatory decisions and transmission work. The generating station's proximity is only one part of the delivery arrangement on which the campus depends.
Power availability belongs in the land price
The initial megawatt allocation, later capacity increases and required network upgrades all affect what a parcel is worth to a data center developer. Curtailment provisions and responsibility for utility construction costs can be just as consequential as the first proposed energization date.
At the hypothetical $100 million project, one year's carrying cost reaches $8 million before lost operating income. A land discount can be overtaken by that expense if the lower-priced property needs another transmission project. Comparing sites means comparing the cost and timing of getting each one into service.
Source equipment around your energization schedule
If your utility date has moved, Meridian Standby Power can look for generators that fit your interim loads and delivery window. Tell us what has to be online, when it has to run, and how long you expect to rely on onsite power.
Find EquipmentSources and further reading
- Dominion Energy's published connection guidance
- Edsall substation and transmission project
- Hornbaker–Devlin project
- December 2024 planning inspector's report
- appeal was refused on February 19, 2025
- July 2024 large power transformer report
- May 1, 2025 clarification
- FERC rejected an amended interconnection agreement
- June 2025, Talen announced an expanded agreement with Amazon